Systima Technologies

R|MILLER Inc began the construction of a manufacturing facility and offices for aerospace and defense company Systima Technologies in January 2020. Located in Snohomish, Washington, the project consists of two tilt-up concrete buildings totaling 86,110 square feet. R|MILLER is providing constructability reviews and design assistance for both the manufacturing facility and tenant improvements. The shell will take 8 months to build, with another two months for the remaining TI work.

Budget: $6,747,056

Schedule: 10 months

Architect: Tahoma Design Group, Hinge Studio LLC

18321 98th Avenue NE, Suite 1, Bothell, WA 98011 | T 425.775.3822 | F 425.977.4898 

  • Facebook Social Icon
  • LinkedIn Social Icon

© 2020 R|MILLER Inc.